Case story

Subgrade Stabilization, Bluford Street and Obermeyer Road, NC

United States, North Carolina, Greensboro

Case Study 

Application

Subgrade Stabilization

Job owner

NC A&T University

Location

Bluford Street and Obermeyer Road, NC

Engineer

ECS, LLC

Product

Mirafi® RS580i

Contractor

Larco Construction

Quantity

2,000/sy

Date of Installation (m/y)

June-July 2011


THE CHALLENGE

NC A&T University needed to replace two sections of roads running through the campus. The road replacements were part of a larger renovation project. When locating existing utilities, several including fiber optics, gas lines and water lines were located within 2 feet of the road surface. The existing subgrade material was a poor silty/sandy soil. While the area was dry during construction, the subgrade still exhibited pumping throughout the area (there may have been a wet layer of soil slightly below the surface). In addition, certain areas saw rutting of up to 5” with the truck traffic in the area.

THE DESIGN

ECS, LLC was brought in to make recommendations on the pavement design. Their standard recommendation for stabilizing soft subgrade is to undercut 18” below the pavement section, install Mirafi® HP270 and place 18” of aggregate base course (ABC) material over it. This recommendation was not an option in these areas due to the location of the utilities. TenCate was called in to assist them with a recommendation requiring less cut and fill. Looking at the higher performance Mirafi® RS580i and using MiraSpec Flexible Pavement Design Software, we were able to reduce the undercut to 9” keeping the excavation clear of utility disruption. This recommendation was based upon the structural number requirement of the pavement and the subgrade having a soaked CBR no lower than 1.5.

THE CONSTRUCTION

The installation of Mirafi® RS580i went well. In lieu of standard ABC material, the decision was made to use recycled concrete with the same gradation as ABC. The material reacted well when placed on the geosynthetic and proof rolled with no problems.

THE PERFORMANCE

The use of Mirafi® RS580i allowed the road to be constructed without having to relocate existing utilities. In addition, the actual construction cost of using the higher performance Mirafi® RS580i versus Mirafi® HP270 was less in this case since 9 inches less undercut and aggregate was needed.

Confinement · Filtration · Mirafi® · Road and Railway Stabilization · RSi-Series · Separation · Soil Reinforcement · Transportation Infrastructure · Woven Geotextiles
Back to the case list
 
TenCate Geosynthetics Americas
Send email +1 (706) 693 2226